This fitting is forged from ZeCor310M. It features excellent hightemperature oxidation resistance and corrosion resistance, and can operate stably for a long time under harsh conditions such as high temperature flue gas, heat treatment and high-temperature process pipelines, with good creep resistance.
Both ends adopt socket welding connection. Pipes are inserted into socket cavities and fixed by fillet welding. Tighten the union nut to compress the sealing surface for reliable sealing. Its core advantage is easy disassembly without cutting the pipe, convenient for maintenance, cleaning and replacement of instrument piping. It covers pressure classes of 3000LB, 6000LB and 9000LB, sizes ranging from 1/8″ to 4″ (DN6-DN100). It is widely applied in petrochemical, energy, metallurgy, high-temperature instrument piping and high-temperature process piping systems.




1. Raw Material InspectionRaw material is ZeCor-310M bar stock. Verify material certificates, perform spectrum test for chemical composition and mechanical properties. Mark heat numbers for full traceability.
2. CuttingCut billets for male end, female end and union nut separately according to drawings. Remove burrs and scale, reserve machining and forging allowance.
3. Heating and Closed Die ForgingHeat billets to specified forging temperature, forge male end, female end and nut blanks separately by closed die forging, control parameters to achieve uniform grain structure.
4. Heat TreatmentSolution treatment is carried out in accordance with dedicated ZeCor-310M procedure to release forging stress and stabilize high-temperature and corrosion resistance.
5. Shot BlastingRemove scale and forging contaminants from blank surface by shot blasting.
6. Precision MachiningCNC turning for socket bore, sealing face, thread and outer profile. Strictly control sealing surface roughness, socket size and thread tolerance to ensure assembly accuracy.
7. Pre-assembly TestAssemble male end, female end and nut, check thread engagement and sealing face contact to avoid jamming and excessive sealing gap.
8. MarkingLaser marking of material, size, pressure class, heat number and standard number.
9. Finished Product InspectionDimensional check, visual inspection, hardness test, PT penetrant testing as required to detect surface defects.
10. Surface PassivationPassivation treatment to improve corrosion resistance.
11. Final Inspection & Document PreparationRecheck all test items, compile MTC, test reports and inspection records.
12. Packing and WarehousingPack the complete set with protective packing, classified storage with full quality documents attached.